Introduction

This post describes the difference between Project Purchase Orders and normal Purchase Orders. Both can be used to buy items for a Project and both to generate Item Transactions on a Project, but nevertheless there are some major differences between both, mainly in the logistic flow.

Project Purchase Orders

A Project Purchase Order can be created directly from the Project form: click Project>Projects>Item task button>Purchase Order.

On Project Purchase Orders, the project number is populated. This seems a minor difference, however a lot of other consequences are triggered by this fact.

The issue inventory transaction generated for a Project Purchase Order is a virtual inventory transaction (Reference is Transaction).

It means the item never arrives in stock. This has import consequences:

  • The item cannot be used in Shipment functionality. As it never arrives in stock upon posting the purchase packing slip, it cannot be added to a Shipment.
  • The item ordered with a Project Purchase Order will never cover a requirement. So if you have a project item requirement and you create a project purchase order for it, the MRP run will still propose a planned purchase order for the item.

These are major disadvantages of using Project Purchase Orders. Nevertheless there are some advantages of using them:

  • The project number allows for easy filtering. Also it is clear for the purchase department for which project the purchase order is intended.
  • Upon posting the purchase packing slip, the item consumption is automatic: no need to post a separate transaction to have the item consumption on the project.

Purchase orders

Another way of buying items for a specific project, is using ‘normal’ Purchase Orders.

You can create a ‘normal’ Purchase order from your project item requirement by clicking the Functions button > Create Purchase Order.

A second way is to run the MRP, which will generate a Planned Purchase Order for your project item requirement. You can Firm this Planned Purchase Order into a ‘normal’ Purchase Order. Just make sure you have marking activated during firming.

Both generate a ‘normal’ Purchase Order which is marked to your project item requirement.

This has some advantages compared to a Project Purchase Order:

  • No virtual transactions are generated for such a Purchase Order. The item arrives in stock upon posting the purchase packing slip. As such the item can be used in Shipment functionality.
  • The Purchase Order will be seen by MRP as a coverage for your project item requirement, avoiding generation of a new Planned Purchase Order. Important to notice here is the condition: it is the Marking which should be activated upon firming.
  • Still, the item consumption on the project can be done rather automatic: upon posting the purchase packing slip, a question will be popped up asking if the consumption should be booked right away on the project.

     
    Important –again- to notice here is that Marking should be activated upon firming.

Minor disadvantage here:

  • Project number is not populated on such ‘normal’ Purchase Orders, so it is less clear for the purchase department to which project the Purchase Order belongs to. Some minor modifications (a new custom field which stores the ProjId) can solve this issue easily.

Comments 7 comments
Anonymous said...

Hi Pat,

I am not able to see the message " Consume items immediately in Project" even though I have the Item consumption checkbox marked in project parameters form. Any clues ?

Patrik Luca said...

I suppose you are on 2012 R2? This checkbox is new in R2 and its purpose is exactly to not show anymore this message. So if you want to see it, uncheck that checkbox.

Anonymous said...

Pat,

Even if I mark it and then create and receive project PO, it is not getting consumed immediately in projects, I mean I am not able to see the item transaction in the project after I receive the PO with this check box marked. Any suggestions ?

Patrik Luca said...

Hi,
there is a second new checkbox in project parameters as of R2 onwards: create item requirements. If this is checked, receiving a project PO does not consume items immediately, unless you choose yes on when the message "Consume items immediately in Project" appears. If this latter message doesn't appear, it is because the second checkbox in project parameters is unchecked.

Samy said...

Hi All,
I am creating the Purchase order using X++,After Creation , i give the Project Id in PO Header it populates the Project Id field to line also. After Confirm the PO , when I do the Product receipt it will not consume the Project cost. how to do this ..........

Please Share your Knowledge


Regards,
Muthusamy

Unknown said...

Hi...your blog helped resolve my issue quickly. I have a question. When using the Item Task > PO process on a fixed price / deferred project....I am using 'service' type items. When posting the PO thru invoice and look at the project, the costs are posting directly to the P&L...where costs posted thru the item requirements are hitting WIP....which is what I was expecting to see on the service items. Thoughts?

Annelies Cartreul said...

Specific question: project A needs 10 pieces of item X, project B needs 5 pieces of item X > Mrp will group de requirements into one PO for both projects > When the PO receipt is posted, is there a possibility then to get the consume items question?

Patrik Luca, Ieper, BELGIUM
Feel free to use or spread all of the content on my blog. In return, linking back to my blog would be greatly appreciated. All my posts and articles are provided "AS IS" with no warranties.

Subscribe feeds via e-mail
Subscribe in your preferred RSS reader

Subscribe feeds rss Most Read Entries

Subscribe feeds rss Recent Entries

Categories

Recommended Books


Subscribe feeds rss Recent Comments

This Blog is part of the U Comment I Follow movement in blogosphere. Means the comment field of this blog is made DOFOLLOW. Spam wont be tolerated.

Blog Archive

My Blog List

Followers

Links